Activities that process multiple entity types may require that an equipment setup or changeover is performed when changing over from one entity type to another.

 

The model used for this example, as well as all of the modeling "how-to" examples, can be found in the ProModel Solutions Café (http://www.promodel.com/solutionscafe/howto/). A video demonstrating this solution can be found here.

Solution

  1. In the activity dialog, click on the Setup tab.
  2. For each entity type requiring a new setup, create a setup record. If all entities have the same setup time, select All as the entity type.
  3. Complete the rest of the data for the setup.
Example

A milling machine is used to mill two different parts with different patterns and tooling requirements. Part A requires a 2 minute setup while Part B requires a 3 minute setup.

Solution

The Setup tab shows the two records which define the setup for the Milling activity.