ALT
Causes a location to be selected as an alternate destination if it has available capacity and the condition for a preceding routing rule is not met. If the ALTERNATE location is unavailable, the entity waits until it becomes available or until the preceding routing rule is satisfied.
ALTERNATE routings are common to all primary routings, except the Probability and User Condition rules, and should therefore be listed after the last primary routing but before any backup routings.
For example, a high-speed machine might be preferred, but alternatively, a slower machine can be used when the faster machine is unavailable.
The rule field of the Routing edit table only. An ALTERNATE routing may be specified after any other type of routing (including other ALTERNATE routings) except for BACKUP, CONTINUE and DEPENDENT routings.
Process Table
Entity... |
Location... |
Operation (min)... |
Shaft |
Drill |
WAIT 3 |
Routing Table
Blk |
Output... |
Destination... |
Rule... |
Move Logic... |
1 |
Shaft |
Lathe1 |
Send 1 |
|
Shaft |
Lathe2 |
Send |
|
|
Shaft |
Lathe3 |
ALT |
|